LHLThe Luxury Hospitality LibraryOn the record
Register/Part IV — Iconic Houses & Destinations/Volume 4 — Desert Retreats/Liwa, Rub’ al Khali, Abu Dhabi
LHL-H-056 · P4-04-03active

Qasr Al Sarab

In the dunes of the Rub’ al Khali near the Liwa oasis, about 200 kilometres from Abu Dhabi International Airport. Developed by the emirate’s Tourism Development and Investment Company at a reported US$176 million, built by Al Jaber from September 2006 and opened in November 2009 under Anantara, the Minor International brand. Roughly two hundred keys in a fortress-style building: the register’s case of the Empty Quarter entered at full hotel scale rather than as a camp.

The house

The house is a state project that acquired an operator. Gulf News reported in the run-up to opening that “TIDC is the investor in the hotel project, Anantara is managing the resort”, named Anantara “a subsidiary of hotel and leisure company Minor International Plc”, and put the figure at “The $176 million (Dh645 million) project, built by Al Jaber Group”. It located the resort “in the Liwa Oasis in the emirate of Abu Dhabi” and said it would be “accessible by road or by a 90-minute flight from Abu Dhabi airport to a hotel-owned private landing strip in the dunes”. Construction had begun in September 2006.

The announced programme was “150 hotel rooms and 60 private villas”; the Tourism Development and Investment Company’s launch notice of 26 November 2009 gave “154 guest rooms, 42 villas” and “10 royal villas”. CNN later described “a fortress-style structure appearing on the edge of dunes” and recorded that the name means “mirage”. Interiors were by Hirsch Bedner Associates with the firm Northpoint, and the house took Best Hotel Spa and Best for Luxury Public Spaces at the Hospitality Design Awards in New York in 2010. The resort now publishes “140 rooms, 14 suites and 53 pool villas”.

What distinguishes it

A state developer built it and a Thai group was brought in to run it The Tourism Development and Investment Company was the investor and Anantara, a subsidiary of Minor International, the manager; Al Jaber Group built it for a reported $176 million. The money, the land and the brief were in place before any hotel company was. Few houses in this Part were assembled in that order.

Two hundred keys in the Empty Quarter At launch the count was 154 guest rooms, 42 villas and 10 royal villas. CNN put it at “154 guestrooms and 52 villas sprawled over 19,000-plus acres”. The Rub’ al Khali had until then been camp country; this is the scale at which the register records it being entered.

The key count has been published four ways 150 rooms and 60 villas were announced before opening; 154 rooms, 42 villas and 10 royal villas at launch; 206 rooms, suites and villas in the 2019 factsheet; and 140 rooms, 14 suites and 53 pool villas on the house’s current pages. The register quotes all four rather than averaging them.

So has the opening date The resort’s own factsheet dates the opening to 7 November 2009. A design trade report of July 2010 gives October 2009. The developer’s launch notice ran on 26 November 2009, and CNN dates the start of construction to 2007 against the developer’s September 2006.

A fort named for something that is not there Qasr Al Sarab translates as “mirage”, and the building answers the name: a fortress-style mass rising at the dune edge rather than a dispersed camp. The bonfire dining and the Thai sala run October to April only, which fixes the house’s outdoor life to half the year.

WHO IT IS NOT FOR

It is about 200 kilometres from Abu Dhabi International Airport and roughly two and a half hours by road from the city, with two hundred keys when it is full: a guest expecting a small desert camp is in the wrong house. The bonfire dining and the outdoor spa sala operate October to April, so a summer stay is largely an indoor one. There is no sea, no town and one road out.

Signature rooms and dates

September 2006Construction begins
The developer’s own date for the start of work by Al Jaber Engineering and Contracting of Abu Dhabi.
2007A second start date enters the record
CNN later states that work began in 2007; the register holds both and reconciles neither.
2009The project is announced for the fourth quarter
At 150 hotel rooms and 60 private villas, a reported $176 million, and a private landing strip in the dunes 90 minutes from Abu Dhabi airport.
7 November 2009The date the resort’s own factsheet gives for opening
A design trade report of the following July instead gives October 2009.
26 November 2009The developer announces the launch
154 guest rooms, 42 villas and 10 royal villas, with an adjacent 9,000 square kilometre wildlife reserve named alongside.
2010Two Hospitality Design Awards in New York
Best Hotel Spa and Best for Luxury Public Spaces, with interiors credited to Hirsch Bedner Associates and the firm Northpoint.
2019The factsheet gives 206 rooms, suites and villas
With the resort placed 200 kilometres from Abu Dhabi International Airport and managed by Anantara Hotels, Resorts & Spas.
2026140 rooms, 14 suites and 53 pool villas
As the house publishes it at the date of reading, a two-and-a-half-hour drive from the city of Abu Dhabi.

Competitive landscape

Sources

What the entry rests on, read 13 October 2026. Each reference records the facts it supports, so a disputed line can be traced to the account it came from.

AnantaraQasr Al Sarab Desert Resort by Anantara, Abu Dhabi, read 13 October 2026the house now publishes 140 rooms, 14 suites and 53 pool villas; the resort is a two-and-a-half-hour drive from the city of Abu Dhabi
AnantaraQasr Al Sarab Desert Resort by Anantara — factsheet, September 2019, read 13 October 2026the 2019 factsheet gives 206 rooms, suites and villas, an opening date of 7 November 2009, 200 kilometres from Abu Dhabi International Airport, and Anantara Hotels, Resorts & Spas as manager
Gulf NewsAnantara set to open luxury hotel in Empty Quarter by year-end, read 13 October 2026TDIC was the investor and Anantara the manager; the project cost a reported $176 million and was built by Al Jaber Group; the announced programme was 150 hotel rooms and 60 private villas, for the fourth quarter of 2009; the resort was announced to open in the fourth quarter of 2009; Anantara is a subsidiary of Minor International and the resort sits in the Liwa Oasis, with a private landing strip announced
Spa OpportunitiesTDIC unveils new Qasr Al Sarab resort, 26 November 2009, read 13 October 2026construction began in September 2006; at launch the count was 154 guest rooms, 42 villas and 10 royal villas; an adjacent wildlife reserve of 9,000 square kilometres was named at launch; TDIC launched the resort, announced 26 November 2009
CNNAbu Dhabi’s hottest hotel: Qasr Al Sarab vs. the desert, read 13 October 2026CNN gives 154 guestrooms and 52 villas over 19,000-plus acres; the building is fortress-style and the name means mirage; CNN dates the start of work to 2007, against the developer’s September 2006
FX DesignQasr Al Sarab Desert Resort in Abu Dhabi honored at Hospitality Design Awards, 23 July 2010, read 13 October 2026interiors were by Hirsch Bedner Associates with the firm Northpoint, and the house won two Hospitality Design Awards in 2010; a design trade report of July 2010 gives the opening as October 2009 and the total as 206 across 154 rooms, 42 villas and 10 royal villas